Saldofy material requirements planning, or MRP, adds up the raw material that planned production orders need according to their recipes, subtracts stock and the quantity already ordered, and shows what has to be bought and by which date.
In manufacturing a material shortage usually comes to light when the work is due to start. The buyer orders from experience and a stock spreadsheet but cannot see which production orders need the goods and when. One material has been ordered twice and another by nobody, because it was in stock, just not in the warehouse that production takes its material from.
Material requirements planning solves this with a calculation that starts from production orders. When every production order knows its recipe and every material knows its supplier and lead time, the need can be gathered into one list that shows both the quantity and the reason. The buyer no longer has to ask whether something is really needed, because the row names the production orders waiting for it.
Keep recipes up to date: components, quantities, scrap percentage and subassemblies.
On the material's product card, fill in the default supplier, purchase price, lead time and, where needed, the reorder quantity.
Plan the production orders. A planned or in-progress production order creates a need, and so does the sub-assembly order of a planned order; a draft you made yourself does not.
Open Manufacturing → Purchase needs and check each row for a material and warehouse: on hand, on order, shortage and suggested quantity.
Check the Needed by column and the production orders the need comes from.
Select rows and choose Create purchase order or Create drafts per supplier.
Review the drafts and send the order to the supplier by e-mail with a PDF attachment.
When the goods arrive, enter the purchase invoice. By default stock and cost arise when the purchase invoice is confirmed, and that is when the shortage disappears.
The need is calculated through the recipe, down through every subassembly to the purchased material, and the scrap percentage is added to the quantity. The calculation uses the recipe version frozen when the production order was planned, not the product's current one.
A production order takes material from its own material warehouse, so the need is calculated per that warehouse. Goods in another warehouse, or a purchase arriving at another warehouse, do not hide the shortage.
The On order column shows the quantity on open purchase orders that has not yet reached stock. By default goods enter stock when the purchase invoice is confirmed, so quantities on unconfirmed purchase invoices are counted here too. A link opens the order the quantity comes from.
Needed by is the earliest day on which, according to the production schedule, a production order needs the material. Each row names the production orders waiting for it.
The supplier comes from the product's default supplier or, if none is set, from the supplier on the last confirmed purchase invoice. The suggested quantity is rounded up to a multiple of the reorder quantity on the product card.
A purchase order line can be linked to a production order. When the goods arrive and the production order's reservation time has come, they are reserved for that production order before another production order or a sales order takes the free stock.
A company that makes metal furniture has a main warehouse and a production warehouse, and its production orders take material from the production warehouse. At the start of the week the planner plans three production orders for dining tables and opens Purchase needs. The first shortage is steel tube, but there is enough of it in the main warehouse. Purchase needs does not hide the shortage behind stock in another warehouse, so instead of buying, the planner makes a transfer between warehouses.
The second row notes that the screws have been received against a purchase order but the purchase invoice has not been entered. The planner asks the accountant to confirm the invoice, and the shortage disappears without a new purchase. Third on the list are table tops and fourth are plastic glides for the legs, which are bought from different suppliers: each has its own default supplier on the product card. The planner selects both rows, chooses Create drafts per supplier and gets two purchase order drafts with the production order numbers in the note. After checking them, the planner e-mails both to the suppliers, and the Needed by column says by which date the goods must be in.
The master schedule deals with finished products: you enter a monthly forecast and Saldofy suggests what to produce and when, based on open sales orders, stock, safety stock and lead time. Material requirements planning comes next: once production orders are planned, it works out the raw material missing for them.
Both sit in the Manufacturing menu under Planning and use the same products, stock and purchase orders. Neither creates a production order or a purchase order on its own; each gives a person the basis for a decision.
Purchase needs is a calculation. An order reaches the supplier only when someone creates the purchase order, reviews it and sends it. The result is only as good as the source data: a wrong recipe, a missing lead time or a purchase invoice not yet entered gives a wrong need.
By default goods enter stock in Saldofy when the purchase invoice is confirmed, not when the receipt is marked. That keeps stock and the general ledger on one document, and Purchase needs shows goods that have been received but not invoiced with a separate note, so that nobody orders them twice. For new purchase orders a company can also enable stock posting on goods receipt (Warehouse → Goods receipts): the receipt then adds the goods to stock straight away and the purchase invoice is matched to the receipt later. The current limits of this mode, for example purchases in euros from Estonian suppliers only, are listed next to the setting.
Last updated
MRP (material requirements planning) is a calculation that starts from production orders: the recipe gives the material quantity for each production order, the quantities are added up, and stock and quantities already ordered are subtracted. The shortage that remains is the purchase need.
No. Purchase needs makes a suggestion and, if you choose, a purchase order draft. The draft has to be reviewed and sent to the supplier with the Send to supplier button, or marked as sent if the order reaches the supplier another way.
A draft is still a sketch whose quantity or warehouse may change. The need arises at planning, when the recipe and routing are frozen. The draft's materials table says so itself. The exception is the sub-assembly order of a planned production order, which counts as a need even as a draft.
The need is calculated per warehouse that the production order takes its material from. Goods in another warehouse are not available to production until they are moved there. If there is enough elsewhere, make a transfer between warehouses and the shortage disappears.
By default stock arises when the purchase invoice is confirmed. If goods have been received against a purchase order but the invoice has not been entered, Purchase needs and the production order's materials table show this with the quantity and the purchase order number. The shortage is covered by entering the purchase invoice, not by a new purchase. If the company has enabled stock posting on goods receipt for new purchase orders, received goods are in stock straight away.
You can close a partly received purchase order with the Close order button. The quantity not delivered is then treated as not coming and Purchase needs no longer counts it as ordered, so the shortage reappears and you can order it elsewhere.
In Manufacturing → Manufactured products you open the breakdown of the product's recipe: components including subassemblies, with stock and shortage. The same structure and the total component need with stock can be downloaded as a PDF or Excel file, for example for a quote or a negotiation with a supplier.
That is your company's choice. In the production orders view you set whether material is reserved immediately at planning, a fixed number of days before the planned start or only when production starts. A later production order's need stays in the plan but does not lock today's free stock.
In a demo we show how a production order becomes a purchase need and a purchase need becomes an order sent to the supplier. The price list shows which plans include the manufacturing module.